The U.S. Environmental Protection Agency and over 16,000 citizens found fault with the Federal Energy Regulatory Commission’s draft environmental review of the Mountain Valley Pipeline project, according to The Roanoke Times. The public comment period for the draft environmental review closed in December.
In a letter to Mountain Valley dated Jan. 13, FERC notes the company made changes to their pipeline route in accordance with recommendations in FERC’s draft Environmental Impact Statement. A public comment period on the changes is open until Feb. 21.
On Jan. 26, FERC submitted a 28-page request seeking additional information from Mountain Valley. The agency’s Final Environmental Impact Statement was originally slated for March 10 but is now delayed indefinitely.
Other Pipeline News
On Dec. 28, 2016, the Southern Environmental Law Center filed a lawsuit against energy company Kinder Morgan in response to the company’s 2014 spill of at least 370,000 gallons of gasoline in South Carolina, according to a statement from the nonprofit law firm.
Citizen and environmental groups are challenging Dominion’s proposed 55-mile pipeline from Moore to Chappells, S.C. The pipeline would impact 255 acres along the route and would require approval from the Federal Energy Regulatory Commission.
On Jan 24., President Trump signed executive orders to advance the Keystone XL and Dakota Access Pipeline projects. The proposed Keystone XL Pipeline, stretching from Canada to Nebraska, was previously rejected by the Obama administration’s Department of State. And the nearly complete Dakota Access Pipeline — spanning from North Dakota to Illinois — was halted by the U.S. Army Corps of Engineers in late 2016 pending further environmental review. Both pipelines face strong opposition. — Carl Blankenship
Related Articles
Latest News
More Stories
‘First Line of Defense’
During Hurricane Helene and its aftermath, rural fire departments and other first responder hubs played critical roles in keeping their communities safe, even without power and cut off from outside support for days or weeks after the storm. Two years later, plenty of work remains to ensure these hubs have the resources they need to operate day to day and be ready when emergencies or natural disasters strike.
The Rocky Road — and Bridge — to Recovery
Hurricane Helene is estimated to have damaged nearly 7,000 private roads and bridges in Western North Carolina. Two years later, many restoration projects are complete, but the journey hasn’t been easy — and isn’t over for others.
After 20 Years, Letcher County Prison Proposal Is Still Alive, Though Obstacles Remain
A $605 million proposal for a federal prison on a former strip mine site in Letcher County, Kentucky, championed by U.S. Rep. Hal Rogers, refuses to die, despite local opposition, a lack of support from the executive branch and numerous other obstacles.
The Washout and Rebuild
For nearly two years, residents of Unicoi County, Tennessee, have had to make do without a hospital after Hurricane Helene destroyed the rural hospital. Ballad Health, which owns the hospital, broke ground on a new location — in another floodplain — in August 2026.
The Shenandoah Salamander
The Shenandoah salamander is a woodland salamander, which has adapted to life at higher elevations away from water. This sparkling rarity lives among the dry leaves, cracked logs, and stony hillocks on the highest peaks of Shenandoah National Park.
‘Foraging Is a Way of Connecting’
Foraging has experienced a modern resurgence, partly because of social media, online groups, the pandemic and people wanting to connect with nature. It also builds community, whether in person or online.
Leave a comment
Your email address will not be published. Required fields are marked *
One response to “Delay in Mountain Valley Pipeline”
-
As a unwilling neighbor to this pipeline, i wonder how laws have come to the point where our property rights are non existent…
Leave a Comment