Under Pressure, Patriot Coal to Phase Out Mountaintop Removal
By Brian Sewell
On Nov. 15, amid bankruptcy litigation and multiple lawsuits, Patriot Coal announced it would begin phasing out mountaintop removal coal mining in Appalachia as part of a settlement over selenium pollution. One of the largest operators in the region, the St. Louis-based spin-off of Peabody Energy is the first major coal operator to announce it will stop using mountaintop removal.
According to the agreement made with the Sierra Club, the Ohio Valley Environmental Coalition and the West Virginia Highlands Conservancy, Patriot will gradually reduce production from surface mines over the next several years and immediately rescind pending permits for new surface mines.
In his statement to U.S. District Judge Robert Chambers, Patriot CEO Ben Hatfield said that Patriot recognizes that its mining operations “impact the communities in which we operate in significant ways,” adding that ending mountaintop removal will reduce the company’s environmental footprint.
Hatfield’s statement, however, focused largely on the financial benefits of reducing the company’s risks as it works through bankruptcy. He added that the settlement is consistent with Patriot’s plan to “focus capital on expanding higher margin metallurgical coal production and limiting thermal coal investments to selective opportunities where geologic and regulatory risks are minimized.”
As the industry faces declining domestic use and competition from natural gas, coal operators in Appalachia are turning to metallurgical coal and focusing on meeting the growing demand overseas. By reducing the regulatory and market risks of continuing to operate mountaintop removal mines, Patriot believes it will increase the likelihood of emerging from bankruptcy as a viable business, able to satisfy its obligations to its nearly 4,000 employees.
Unsurprisingly, representatives of environmental groups and the coal industry saw the news differently. Executive director of the Sierra Club Michael Brune said that “Patriot Coal may be the first company to cease mountaintop removal mining but, because of the tireless efforts of committed volunteers and community organizations, it certainly won’t be the last.” On the other hand, West Virginia Coal Association President Bill Raney remarked that “It’s one company trying to restructure itself. This doesn’t change anything. I don’t think you can apply this universally across the industry or across the state.”
As part of the agreement, Patriot is able to delay $27 million in selenium pollution compliance costs until 2014, improving the company’s ability to pay an estimated $400 million in long-term selenium cleanup costs.
Patriot Coal filed for bankruptcy in July after reporting considerable losses since 2010. On Nov. 27, a federal judge granted a request by Patriot employees to move the bankruptcy litigation from New York City to St. Louis, where Patriot and parent companies Peabody Energy and Arch Coal are based.
Related Articles
Latest News
More Stories
Neighbors Help Neighbors
A photo essay that celebrates the volunteer spirit of the grassroots group Hurricane Helene WNC and speaks to the resourcefulness, collaboration and hard work embodied by thousands and thousands of volunteers, first responders and aid workers across the region after Hurricane Helene.
Halloween Approaches, and Night School Is in Session
The House of Art in Bluefield, West Virginia, looks like a haunted tower, making it the perfect location for its sixth annual haunt event: Night School. The Night School will be open every Friday and Saturday night through Oct. 31.
‘The Most Perfect Act of Love’
Hundreds of people attended the second annual Affirming Sumner Pride celebration on a 24-acre farm dubbed “Fruity Farm” in Bethpage, Sumner County, Tennessee.
Signs of Life: Endangered Bats Found in Nantahala for First Time in More Than a Decade
In the Nantahala National Forest, a team of biologists spotted Indiana bats, an endangered species that hasn’t been seen in North Carolina for the last 11 years.
‘First Line of Defense’
During Hurricane Helene and its aftermath, rural fire departments and other first responder hubs played critical roles in keeping their communities safe, even without power and cut off from outside support for days or weeks after the storm. Two years later, plenty of work remains to ensure these hubs have the resources they need to operate day to day and be ready when emergencies or natural disasters strike.
The Rocky Road — and Bridge — to Recovery
Hurricane Helene is estimated to have damaged nearly 7,000 private roads and bridges in Western North Carolina. Two years later, many restoration projects are complete, but the journey hasn’t been easy — and isn’t over for others.
Leave a comment
Your email address will not be published. Required fields are marked *
Leave a Comment